Status of every project in $16b mining pipeline
THERE are dozens of mining projects worth more than $16 billion in the pipeline for the Isaac and Whitsunday region.
That's according to the Greater Whitsunday Alliance Regional Projects Development Register update.
The register highlights the projects planned across the region, including a dollar figure, start and finish dates and project status.
GW3 chief executive Kylie Porter said the data presented in the register demonstrated the region's economic strength and provided interested stakeholders with a better understanding of development activity within the region.
More stories:
New mine: CQ coal project promises 2350 jobs
WATCH: Work starts on Adani's open cut mine
Explained: Status of 7 major Bowen Basin mines
She said the total value of projects listed was up $9.3 billion from last year, with 38 more projects listed.

The Regional Projects Development Register is produced annually.
The data was sourced through Cordell Connect, a database for residential, commercial, industrial, community, engineering and mining projects.
Full list of mining projects in pipeline (including construction services etc)
Mackay: Nil
Isaac:
ANGLO AMERICAN AQUILA PROJECT:
Cost: $1,000,000
Start: January 14, 2021
Completion: January 14, 2022
Status: Possible
ANGLO AMERICAN AQUILA PROJECT - BSL AND AFC DRIVES OVERHAUL
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - CONTINUOUS MINER CM003 OVERHAUL
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - LHDS AND GRADER OVERHAUL
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - LONGWALL SHIELDS AND PANS
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - REAL TIME GAS MONITORING
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - SHEARER OVERHAUL
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations
ANGLO AMERICAN AQUILA PROJECT - SURFACE CONVEYOR
Cost: $1,000,000.00
Start: January 14, 2021
Completion: January 14, 2022
Status: Registrations

ANTHONY MOLYBDENUM PROJECT
Cost: $4,000,000.00
Start: July 1, 2026
Completion: December 31, 2036
Status: Early
ATP814P BOWEN BASIN CSG & SHALE PROJECT
Cost: $5,000,000
Start: July 1, 2022
Completion: December 31, 2027
Status: Possible
BEE CREEK THERMAL COAL PROJECT
Cost: $2,000,000
Start: May 22, 2019
Completion: Not available
Status: Not available
BELYANDO GOLD PROJECT
Cost: $4,000,000
Start: July 15, 2023
Completion: December 31, 3038
Status: Early
BLACKRIDGE GOLD PROJECT
Cost: $2,000,000
Start: May 31, 2028
Completion: May 31, 2038
Status: Early
BLAIR ATHOL COAL OPERATIONS RECOMMENCEMENT
Cost: $10,000,000
Start: August 30, 2017
Completion: August 30, 2024
Status: Commenced
BLAIR ATHOL COAL OPERATIONS RECOMMENCEMENT - SOLAR POWER STATION
Cost: $20,000,000
Start: November 15, 2017
Completion: February 15, 2018
Status: Commenced
BROUGHTON COAL PROJECT
Cost: $10,000,000
Start: June 15, 2026
Completion: December 31, 2036
Status: Deferred
BROUGHTON COAL PROJECT - MINE INFRASTRUCTURE AREA
Cost: $2,000,000
Start: January 24, 2025
Completion: June 24, 2025
Status: Deferred
BROUGHTON COAL PROJECT - PROCESSING PLANT
Cost: $10,000,000
Start: March 15, 2025
Completion: December 31, 2025
Status: Deferred
BROUGHTON COAL PROJECT - RAIL LOOP & TRAIN LOAD OUT FACILITY
Cost: $2,000,000
Start: January 20, 2025
Completion: July 20, 2025
Status: Deferred
BYERWEN COAL PROJECT
Cost: $1,760,000,000
Start: December 15, 2017
Completion: December 31, 2064
Status: Commended
CARMICHAEL RAIL & COAL MINE PROJECT
Cost: $2,000,000,000
Start: October 1, 2019
Completion: December 1, 2021
Status: Commenced
CAVAL RIDGE SOUTHERN CIRCUIT
Cost: $200,000,000
Start: October 20, 2018
Completion: June 20, 2028
Status: Commenced
CHINA STONE COAL PROJECT
Cost: $6,000,000,000
Start: June 6, 2019
Completion:
Status: Possible
CHINA STONE COAL PROJECT - ACCOMMODATION VILLAGE
Cost: $10,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - AIRSTRIP
Cost: $5,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - COAL HANDLING & PREPARATION PLANTS
Cost: $20,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - POWER STATION
Cost: $50,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - POWER STATION WASTE STORAGE FACILITY
Cost: $2,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - RAIL LOOP & TRAIN LOADING FACILITIES
Cost: $30,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - STOCKPILES
Cost: $2,000,000
Start: June 6, 2019
Status: Possible
CHINA STONE COAL PROJECT - WORKSHOPS
Cost: $5,000,000.00
Start: June 6, 2019
Status: Possible
CLERMONT JOINT VENTURE COPPER GOLD PROJECT - DISNEY
Cost: $5,000,000.00
Start: July 15, 2025
Completion: December 31, 2035
Status: Early
CLERMONT JOINT VENTURE COPPER PROJECT
Cost: $2,000,000.00
Start: July 1, 2025
Completion: December 31, 2035
Status: Early
CLERMONT GOLD PROJECT
Cost: $2,000,000.00
Start: July 1, 2027
Completion: December 31, 2036
Status: Early
CODRILLA COAL PROJECT
Cost: $50,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - ADMINISTRATION BUILDING
Cost: $1,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - BATHHOUSE
Cost: $1,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - DAMS
Cost: $2,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - ELECTRICITY LINE & SUBSTATION
Cost: $2,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - FUEL STORAGE AREA
Cost: $1,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - HAUL ROAD
Cost: $2,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - SEWERAGE PLANT
Cost: $1,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - WATER PIPELINE
Cost: $2,000,000.00
Start: March 27, 2018
Status: Possible
CODRILLA COAL PROJECT - WORKSHOP AREA
Cost: $1,000,000.00
Start: March 27, 2018
Status: Possible
DEGULLA COAL PROJECT
Cost: $2,000,000.00
Start: September 13, 2017
Status: Possible
DENHAM PARK COAL PROJECT
Cost: $2,000,000.00
Start: March 15, 2028
Completion: March 15, 2038
Status: Early
DRUMMOND COAL PROJECT
Cost: $2,000,000.00
Start: July 15, 2025
Completion: December 31, 2035
Status: Early
DYSART EAST COAL MINE PROJECT
Cost: $5,000,000.00
Start: May 27, 2023
Completion: May 27, 2042
Status: Possible
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT
Cost: $1,130,000,000.00
Start: September 1, 2025
Completion: December 31, 2049
Status: Early
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - 132KV 11KV ELECTRICAL SWITCHYARD
Cost: $1,000,000.00
Start: September 27, 2020
Completion: September 27, 2021
Status: Registrations
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - 701A WATER STORAGE DAM CONSTRUCTION
Cost: $1,000,000.00
Start: September 27, 2020
Completion: September 27, 2021
Status: Registrations
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - DEVELOPMENT EQUIPMENT - PROCUREMENT
Cost: $1,000,000.00
Start: September 27, 2020
Completion: September 27, 2021
Status: Registrations
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - IN-SEAM DEVELOPMENT
Cost: $1,000,000.00
Start: October 11, 2020
Completion: October 11, 2021
Status: Registrations
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - LONGWALL EQUIPMENT - PROCUREMENT
Cost: $1,000,000.00
Start: September 26, 2020
Completion: September 27, 2021
Status: Registrations
EAGLE DOWNS JOINT VENTURE METALLURGICAL COAL PROJECT - RO WATER TREATMENT PLANT
Cost: $1,000,000.00
Start: September 27, 2020
Completion: September 27, 2021
Status: Registrations
EAGLEFIELD COAL OPERATIONS EXPANSION
Cost: $80,000,000.00
Start: April 26, 2018
Status: Possible
EASTERN GALILEE COAL PROJECT
Cost: $2,000,000.00
Start: January 24, 2018
ELLENSFIELD COAL OPERATIONS EXPANSION
Cost: $640,000,000.00
Start: September 12, 2017
FOXLEIGH COAL OPERATIONS EXTENSION - FOXLEIGH PLAINS
Cost: $50,000,000.00
Start: May 22, 2019
FOXLEIGH COAL OPERATIONS EXTENSION - FOXLEIGH PLAINS MINE INDUSTRIAL AREA
Cost: $10,000,000.00
Start: October 12, 2018
HAIL CREEK COAL OPERATIONS EXPANSION
Cost: $750,000,000.00
Start: July 1, 2022
Completion: June 20, 2024
Status: Deferred
HILLALONG COAL PROJECT
Cost: $75,000,000.00
Start: June 15, 2025
Completion: December 31, 2031
Status: Possible
HILLALONG COAL PROJECT - ACCOMMODATION CAMP
Cost: $2,000,000.00
Start: February 3, 2024
Completion: July 31, 2024
Status: Possible
HILLALONG COAL PROJECT - COAL HANDLING & PREPARATION PLANT
Cost: $5,000,000.00
Start: December 15, 2024
Completion: June 15, 2025
Status: Possible
HILLALONG COAL PROJECT - HAUL ROADS
Cost: $2,000,000.00
Start: December 21, 2024
Completion: April 20, 2025
Status: Possible
HILLALONG COAL PROJECT - ROM COAL STOCKPILE
Cost: $2,000,000.00
Start: December 15, 2024
Completion: May 15, 2025
Status: Possible
HILLALONG COAL PROJECT - SEWAGE TREATMENT PLANT
Cost: $3,000,000.00
Start: December 15, 2024
Completion: August 15, 2025
Status: Possible
HILLALONG COAL PROJECT - WATER SUPPLY PIPELINE
Cost: $4,000,000.00
Start: November 25, 2024
Completion: March 25, 2025
Status: Possible
HILLALONG JOINT VENTURE COAL PROJECT
Cost: $2,000,000.00
Start: October 13, 2027
Completion: October 13, 2037
Status: Early
IRONBARK 1 COAL PROJECT
Cost: $20,000,000.00
Start: February 1, 2020
Completion: February 1, 2040
Status: Possible
ISAAC DOWNS COAL PROJECT
Cost: $20,000,000.00
Start: June 14, 2022
Completion: June 14, 2032
Status: Early
ISAAC PLAINS EAST COAL PROJECT
Cost: $7,800,000.00
Start: August 20, 2018
Completion: June 20, 2026
Status: Commenced
ISAAC PLAINS UNDERGROUND MINE
Cost: $2,000,000.00
Start: March 8, 2022
Completion: March 8, 2023
Status: Early
ISAAC RIVER COKING COAL PROJECT
Cost: $2,000,000.00
Start: December 7, 2027
Completion: December 7, 2037
Status: Early
KARIN COKING COAL PROJECT
Cost: $2,000,000.00
Start: March 8, 2028
Completion: March 8, 2038
Status: Early
MOORLANDS COAL PROJECT
Cost: $148,000,000.00
Start: January 24, 2018
MOORVALE COAL OPERATIONS - UNDERGROUND PROJECT
Cost: $5,000,000.00
Start: April 26, 2018
Cost: Possible
MORANBAH COAL PROJECT
Cost: $2,000,000.00
Start: June 9, 2019
MORANBAH SOUTH COAL PROJECT
Cost: $1,000,000,000.00
Start: March 27, 2018
Status: Possible
MOUNT CLARK WEST COPPER GOLD PROJECT
Cost: $2,000,000.00
Start: August 2, 2028
Completion: August 2, 2038
Status: Early
MOUNT HILLALONG/KENNIS CREEK JOINT VENTURE COAL PROJECT
Cost: $2,000,000.00
Start: November 8, 2018
NEW LENTON COAL PROJECT
Cost: $10,000,000.00
Start: July 15, 2027
Completion: July 31, 2047
Status: Possible
NEW LENTON COAL PROJECT - COAL HANDLING & PREPARATION PLANT
Cost: $5,000,000.00
Start: July 15, 2027
Completion: June 15, 2025
NEW LENTON COAL PROJECT - INFRASTRUCTURE
Cost: $4,000,000.00
Start: January 1, 2025
Completion: August 4, 2025
Status: Possible
NEW LENTON COAL PROJECT - POWER SUPPLY
Cost: $1,000,000.00
Start: January 25, 2025
Completion: March 25, 2025
Status: Possible
NEW LENTON COAL PROJECT - RAIL LOAD OUT FACILITY
Cost: $1,000,000.00
Start: January 25, 2025
Completion: March 25, 2025
Status: Possible
NEW LENTON COAL PROJECT - ROAD REALIGNMENT
Cost: $1,000,000.00
Start: January 25, 2025
Completion: April 25, 2025
Status: Possible
NEWLANDS COAL OPERATIONS VILLAGE EXTENSION
Cost: $2,000,000.00
Start: 8/03/2018
NEWLANDS COAL OPERATIONS EASTERN CREEK & NORTHERN UNDERGROUND EXTENSIONS
Cost: $155,000,000.00
Start: July 17, 2018
Status: Possible
NORTH GOONYELLA UNDERGROUND FIBRE INSTALLATION
Cost: $1,000,000.00
Start: October 4, 2019
OAKY CREEK COAL OPERATIONS - OFFICES & MUSTER AREA
Cost: $3,000,000.00
Start: December 10, 2018
OLIVE DOWNS JOINT VENTURE COAL PROJECT
Cost: $1,009,000,000.00
Start: July 1, 2021
Completion: December 31, 2029
Status: Possible
OLIVE DOWNS JOINT VENTURE COAL PROJECT - ACCESS ROADS
Cost: $3,000,000.00
Start: June 15, 2021
Completion: December 30, 2021
Status: Possible
OLIVE DOWNS JOINT VENTURE COAL PROJECT - ADMINISTRATION BUILDING
Cost: $1,500,000.00
Start: June 15, 2021
Completion: December 30, 2021
Status: Possible
OLIVE DOWNS JOINT VENTURE COAL PROJECT - AMENITIES BUILDINGS
Cost: $2,000,000.00
Start: February 15, 2021
Completion: June 30, 2021
Status: Possible
OLIVE DOWNS JOINT VENTURE COAL PROJECT - CRIB ROOMS
Cost: $1,200,000.00
Start: February 2, 2021
Completion: June 30, 2021
Status: Possible
OLIVE DOWNS JOINT VENTURE COAL PROJECT - HAUL ROADS
Cost: $5,000,000.00
Start: February 2, 2021
Completion: June 30, 2021
Status: Possible
RED HILL COAL PROJECT
Cost: $100,000,000.00
Start: January 1, 2028
Completion: June 30, 2052
Status: Deferred
ROCKWOOD COAL PROJECT
Cost: $10,000,000.00
Start: July 15, 2025
Completion: December 1, 2033
Status: Early
SARAJI EAST COAL PROJECT
Cost: $100,000,000.00
Start: October 20, 2023
Completion: October 20, 2033
Status: Early
SARAJI EAST COAL PROJECT - ACCOMMODATION FACILITY
Cost: $2,000,000.00
Start: January 15, 2023
Completion: June 30, 2023
Status: Early
SARAJI EAST COAL PROJECT - COAL HANDLING & PREPARATION PLANT
Cost: $2,000,000.00
Start: February 1, 2023
Completion: July 31, 2023
Status: Early
SARAJI EAST COAL PROJECT - CONVEYOR SYSTEM
Cost: $2,000,000.00
Start: March 15, 2023
Completion: November 15, 2023
Status: Early
SARAJI EAST COAL PROJECT - GAS DRAINAGE BORES
Cost: $1,000,000.00
Start: June 27, 2023
Completion: December 27, 2023
Status: Early
SARAJI EAST COAL PROJECT - MINE INFRASTRUCTURE AREA
Cost: $2,000,000.00
Start: February 15, 2023
Completion: December 15, 2023
Status: Early
SARAJI EAST COAL PROJECT - POWERLINE RELOCATION
Cost: $1,000,000.00
Start: June 27, 2023
Completion: December 27, 2023
Status: Early
SARAJI EAST COAL PROJECT - RAIL SPUR & BALLOON LOOP & SIGNALLING SYSTEM
Cost: $2,000,000.00
Start: April 1, 2023
Completion: November 10, 2023
Status: Early
SARAJI EAST COAL PROJECT - ROM STOCKPILE & PRODUCT STOCKPILE PADS
Cost: $2,000,000.00
Start: March 15, 2023
Completion: October 30, 2023
Status:
SARAJI EAST COAL PROJECT - TAILINGS STORAGE FACILITY
Cost: $1,000,000.00
Start: June 27, 2023
Completion: December 27, 2023
Status: Early
SARAJI EAST COAL PROJECT - UNDERGROUND COAL MINE
Cost: $5,000,000.00
Start: June 20, 2023
Completion: February 20, 2024
Status: Early
SARAJI EAST COAL PROJECT - WATER PIPELINE RELOCATION
Cost: $1,000,000.00
Start: June 20, 2023
Completion: December 20, 2023
Status: Early
SIENNA & ELECTRA COAL PROJECT
Cost: $5,000,000.00
Start: March 26, 2018
Status: Deferred
SOUTH CLERMONT COAL PROJECT
Cost: $2,000,000.00
Start: July 1, 2024
Completion: December 31, 2034
Status: Deferred
VERMONT EAST COAL PROJECT
Cost: $5,000,000.00
Start: March 27, 2018
WILLUNGA COAL PROJECT
Cost: $5,000,000.00
Start: April 26, 2018
Status: Deferred
WILSON CREEK COAL PROJECT
Cost: $2,000,000.00
Start: March 8, 2028
Completion: March 8, 2038
Status: Early
WINCHESTER SOUTH COKING COAL PROJECT
Cost: $10,000,000.00
Start: April 5, 2024
Completion: April 15, 2054
Status: Early
WOLFGANG COAL PROJECT
Cost: $2,000,000.00
Start: March 8, 2028
Completion: March 8, 2038
Status: Early
Subscriber benefits:
Five ways to get more from your digital subscription
WATCH: Your guide to reading the Daily Mercury online
Your questions about the new Daily Mercury format answered
Whitsunday:
ABBOT POINT DEVELOPMENT WORKS - ONSHORE INVESTIGATION DRILLING
Cost: $5,000,000.00
Start: 10/06/2021
Completion: 10/12/2022
Status: Possible
ATP 688P BOWEN BASIN CSG PROJECT - TILBROOK/MOUNT SAINT MARTIN
Cost: $10,000,000.00
Start: 15/07/2023
Completion: 31/12/2033
Status: Early
EDINBURGH PARK GOLD PROJECT
Cost: $2,000,000.00
Start: 10/05/2025
Completion: 10/05/2035
Status: Early
GALILEE (CHINA FIRST) COAL PROJECT - RAIL CORRIDOR
Cost: $100,000,000.00
Start: 12/10/2018
Status: Possible
HILL 212 GOLD SILVER PROJECT
Cost: $2,000,000.00
Start: 2/08/2028
Completion: 2/08/2038
Status: Early
JAX COAL PROJECT
Cost: $15,000,000.00
Start: 15/07/2012
Completion: 31/12/2025
Status: Commenced
JOHNNY CAKE GOLD SILVER COPPER PROJECT
Cost: $2,000,000.00
Start: 15/07/2025
Completion: 31/12/2033
Status: Early
MOUNT CARLTON UNDERGROUND MINE
Cost: $60,000,000.00
Start: 10/01/2021
Completion: 10/01/2025
Status: Commenced
MOUNT COOLON GOLD PROJECT
Cost: $25,170,000.00
Start: 11/12/2025
Completion: 11/12/2035
Status: Possible
MOUNT COOLON GOLD PROJECT - CIL PLANT
Cost: $12,112,000.00
Start: 7/12/2024
Completion: 7/12/2025
Status: Possible
MOUNT COOLON GOLD PROJECT - EUGENIA MINING INFRASTRUCTURE
Cost: $1,231,000.00
Start: 7/12/2024
Completion: 7/12/2025
Start: Possible
MOUNT COOLON GOLD PROJECT - HEAP LEACH PLANT
Cost: $8,312,000.00
Start: 7/12/2024
Completion: 7/12/2025
Status: Possible
MOUNT COOLON GOLD PROJECT - KOALA MINING INFRASTRUCTURE
Cost: $1,033,000.00
Start: 7/12/2025
Completion: 7/12/2026
Status: Possible
NORTH GAILILEE BASIN RAIL (NGBR) CARMICHAEL RAIL PROJECT
Cost: $100,000,000.00
Start: 1/12/2021
Completion: 30/12/2023
Status: Firm
TWIN HILLS GOLD PROJECT
Cost: $2,000,000.00
Start: 11/01/2028
Completion: 11/01/2038
Status: Early